The Project

The refrigerant for the entire meat works is supplied from the ammonia chiller engine room.   This includes the complex and process-critical blast tunnel continuous chilling system.  Both systems required complete control system upgrades.  Models were created to allow new control systems to be verified before plant shutdowns for commissioning.

Results

  • Commissioning of both systems with no impacts on production.